Saturday, May 21, 2011
7 work Sun
Heard drilling being carried out. Went out to see that a small awning has been put in place which I assume it will be done but was assured it won't be. So there!
Thursday, May 19, 2011
Saturday, May 14, 2011
Current Status
About 5 months have passed since my last status update.
5st:
1 house (6) is doing active renovation since it started on 10 Jan 2011.
1 house (7) is doing preparation for moving in since work started 13 Oct 2010.
2 houses have moved in since Nov 2010:
- 4 around 15 March 2011
- 18 around 12 May 2011
Stats:
4, 8, 10, 12, 14, 16, 18, 20, 22, 24, 26, 28, 30 (13/15 = 87%)
3, 5, 9, 11, 15, 17, 19, 21 (8/12 = 67%)
21 in out of 27 so 78% in.
21 months since VP and 78% houses occupied on this street.
5st:
1 house (6) is doing active renovation since it started on 10 Jan 2011.
1 house (7) is doing preparation for moving in since work started 13 Oct 2010.
2 houses have moved in since Nov 2010:
- 4 around 15 March 2011
- 18 around 12 May 2011
Stats:
4, 8, 10, 12, 14, 16, 18, 20, 22, 24, 26, 28, 30 (13/15 = 87%)
3, 5, 9, 11, 15, 17, 19, 21 (8/12 = 67%)
21 in out of 27 so 78% in.
21 months since VP and 78% houses occupied on this street.
Friday, May 13, 2011
18 red cloth
On the evening of May 12, 2011 (Thu) I noticed a piece of red cloth hanging around the main door of 18 so that means they have moved in. I think they have moved in ceremonially only because there do not seem to be any activities in the house and I do not notice any occupants at all.

From and including: Monday, 23 August 2010 (reno work started)
To and including: Thursday, 12 May 2011
It is 263 days from the start date to the end date, end date included
Or 8 months, 20 days including the end date

From and including: Monday, 23 August 2010 (reno work started)
To and including: Thursday, 12 May 2011
It is 263 days from the start date to the end date, end date included
Or 8 months, 20 days including the end date
Tuesday, May 3, 2011