Saturday, October 29, 2011
Even nos all in
Today we saw another household "full of things in lorry" moved in. Thus the even nos are all done now.
Saturday, October 15, 2011
Sunday, October 2, 2011
Saturday, October 1, 2011
Thursday, September 22, 2011
Wednesday, September 21, 2011
Tuesday, September 20, 2011
Friday, September 16, 2011
Planting trees
Thursday, September 1, 2011
Current status
Some changes in the stats as two others moved in around 30 August 2011
5st:
2 houses (2 and 25) are doing active renovation since end July 2011.
1 house (7) has still not moved in yet despite the house being ready since mid June 2011.
2 houses have moved in since Nov 2010:
- 6 around 30 Aug 2011
- 1 around mid Aug 2011 (1 or 2 cars parked overnight so it is assumed that someone is spending the night in the house although the moving in process is still in progress).
Stats:
4, 6, 8, 10, 12, 14, 16, 18, 20, 22, 24, 26, 28, 30 (14/15 = 93%)
1, 3, 5, 9, 11, 15, 17, 19, 21 (9/12 = 75%)
23 in out of 27 so 85% in.
26 months since VP and 85% houses occupied on this street.
5st:
2 houses (2 and 25) are doing active renovation since end July 2011.
1 house (7) has still not moved in yet despite the house being ready since mid June 2011.
2 houses have moved in since Nov 2010:
- 6 around 30 Aug 2011
- 1 around mid Aug 2011 (1 or 2 cars parked overnight so it is assumed that someone is spending the night in the house although the moving in process is still in progress).
Stats:
4, 6, 8, 10, 12, 14, 16, 18, 20, 22, 24, 26, 28, 30 (14/15 = 93%)
1, 3, 5, 9, 11, 15, 17, 19, 21 (9/12 = 75%)
23 in out of 27 so 85% in.
26 months since VP and 85% houses occupied on this street.
Tuesday, August 30, 2011
6 in
Wednesday, August 24, 2011
Umbrella tree
Monday, August 1, 2011
Current Status
Monday, July 25, 2011
3 reno work
Today I notice 3 other houses have started reno work.
All 3 are corner units. All involved breaking down walls and moving walls and extending the house.
Two of four did many concrete pillars.
Two of five just use wood pillars which means less work I think.
25 of 5 will add another room to the ground floor.
I believe that all 3 of them will only complete the reno and move in before CNY next year.
All 3 are corner units. All involved breaking down walls and moving walls and extending the house.
Two of four did many concrete pillars.
Two of five just use wood pillars which means less work I think.
25 of 5 will add another room to the ground floor.
I believe that all 3 of them will only complete the reno and move in before CNY next year.
Tuesday, July 5, 2011
Friday, June 24, 2011
Monday, June 20, 2011
Saturday, June 18, 2011
Tuesday, June 14, 2011
Monday, June 13, 2011
Soil ready
Sunday, June 12, 2011
Saturday, May 21, 2011
7 work Sun
Thursday, May 19, 2011
Saturday, May 14, 2011
Current Status
About 5 months have passed since my last status update.
5st:
1 house (6) is doing active renovation since it started on 10 Jan 2011.
1 house (7) is doing preparation for moving in since work started 13 Oct 2010.
2 houses have moved in since Nov 2010:
- 4 around 15 March 2011
- 18 around 12 May 2011
Stats:
4, 8, 10, 12, 14, 16, 18, 20, 22, 24, 26, 28, 30 (13/15 = 87%)
3, 5, 9, 11, 15, 17, 19, 21 (8/12 = 67%)
21 in out of 27 so 78% in.
21 months since VP and 78% houses occupied on this street.
5st:
1 house (6) is doing active renovation since it started on 10 Jan 2011.
1 house (7) is doing preparation for moving in since work started 13 Oct 2010.
2 houses have moved in since Nov 2010:
- 4 around 15 March 2011
- 18 around 12 May 2011
Stats:
4, 8, 10, 12, 14, 16, 18, 20, 22, 24, 26, 28, 30 (13/15 = 87%)
3, 5, 9, 11, 15, 17, 19, 21 (8/12 = 67%)
21 in out of 27 so 78% in.
21 months since VP and 78% houses occupied on this street.
Friday, May 13, 2011
18 red cloth
On the evening of May 12, 2011 (Thu) I noticed a piece of red cloth hanging around the main door of 18 so that means they have moved in. I think they have moved in ceremonially only because there do not seem to be any activities in the house and I do not notice any occupants at all.

From and including: Monday, 23 August 2010 (reno work started)
To and including: Thursday, 12 May 2011
It is 263 days from the start date to the end date, end date included
Or 8 months, 20 days including the end date

From and including: Monday, 23 August 2010 (reno work started)
To and including: Thursday, 12 May 2011
It is 263 days from the start date to the end date, end date included
Or 8 months, 20 days including the end date
Tuesday, May 3, 2011
Monday, April 11, 2011
Saturday, March 26, 2011
Additional awning?
A (independent team - not affiliated to any organization I believe) couple (a man and a woman) have been working on putting up these additional metal frame onsite on and off for a few days now. They do everything onsite - cutting the iron rods and painting them. Are those gutters at the end? Where will the downpipe be installed?

Tuesday, March 15, 2011
Saturday, February 26, 2011
Aircon and gatelights
Change gate lights
Friday, February 25, 2011
Putting up grilles
Started putting up grilles and changing the main gate to roller folding gate. Changed the side gate too but did not finish due to heavy rain in the evening.
Saturday, February 19, 2011
Thursday, February 17, 2011
Downpipe
A rectangular downpipe was installed for the MBR balcony roof and was painted to be the same light greenish colour as the walls. One end joins the gutter of the roof of the front porch.
The downpipe for the back roof.
It has a few bends on top of the roof of the back extension and then goes on top of the roof and with one open end in the gutter of the roof of the back extension.
The downpipe for the back roof.
It has a few bends on top of the roof of the back extension and then goes on top of the roof and with one open end in the gutter of the roof of the back extension.